VT MAE MRO Hangar at PNS

VT MAE MRO Hangar Progress banner

Project Description


In September of 2014, Mayor Ashton Hayward signed the final lease agreement between the City of Pensacola and VT Mobile Aerospace Engineering Inc. (VT MAE) for the development of a Maintenance, Repair Overhaul (MRO) Hangar at the Pensacola International Airport.

Per the lease, the City of Pensacola will construct an aircraft hangar complex on nearly 19 acres at the Pensacola International Airport and lease the facilities to VT MAE for a 30-year term. The original configuration was designed to accommodate two wide-body aircraft inside of a 160,000 square foot MRO facility. In 2015, the design configuration was expanded to 173,452 square foot facility and will now have the ability to accommodate either two Boeing 777’s, four Boeing 757’s, or six Airbus A-320 sized aircraft.

The new MRO Hangar at the Pensacola International Airport (PIA) will create 400 new jobs and will bring a new industry to the area. VT MAE will hire skilled personnel including Master Airplane Technicians, Aircraft Inspectors, Master Structures Technicians, Sheet Metal Mechanics, and Avionics Technicians. Local economic development agencies, local educational institutions, and VT MAE have worked together to implement training programs to create a sustainable workforce.

By working with VT MAE, Pensacola will be able to create quality, high-paying jobs and cement Pensacola's position as a true contender for aviation and aerospace industry investments. This partnership aligns well with the City's regional goals to create a robust aerospace cluster and to improve business and job opportunities for the citizens of Pensacola and Escambia County.

Design and construction of the $46 million dollar project is being made possible through a combination of funds from the State of Florida/Florida Department of Transportation (FDOT), the City of Pensacola, Escambia County, VT MAE, and the Industry Recruitment, Retention and Expansion Fund.

The newly configured MRO Hangar at the Pensacola International Airport broke ground on October 28, 2016 and construction will last approximately 16 months. The facility is expected to be operational in early 2018.

 

Upcoming Scheduled Work 


  
Work Scheduled for Week Ending 10/20/17:
  • Continue installation of vertical panels on the plan north side of the hangar.
  • Begin sky light installation.
  • Continue concrete pours in the hangar to include slab on grade in areas.
  • Begin block walls.
  • Start layout for interior studs.
  • Start installation of fire proofing.
  • Continue rough-in work for plumbing and electrical.
  • Continue installation of FRP duct and huffer pipe.
  • Continue grading and sodding for the southern drainage ditch.
  • Continue sewer and water installation along the entrance road.
  • Start grading for the turn lane along Langley Avenue at the entrance road.
  • Start installation of the permanent fence.
  • Continue storm sewer installation in the North parking lot.
  • Continue fire protection rough-in.

October 2017 Progress 


  
Work Completed, Week Ending 10/13/17:
  • Pumped water from Hurricane Nate, but did not sustain any actual damage from the storm.
  • Continued installing vertical panels on the plan north hangar wall and began siding between the high and low  bay areas.
  • Completed bolt tightening and passed inspection.
  • Continued installing bracing in the mezzanine area.
  • Began excavating hangar door foundation and constructing forms.
  • Continued plumbing installation.
  • Continued installation of hangar lightning protection and grounding.
  • Continued installation of mechanical FRP duct.
  • Continued installation of duct hangars.
  • Completed wall framing in the administrative area.
  • Continued sheetrock installatin in the administrative area.
  • Continued electrical overhead and wall rough-in in the administrative area and hangar.
  • Continued construction of the southern drainage ditch with grading/sodding and installed structures CD-1 and CD-2.
  • Poured the headwall for structure S-005.
  • Completed all asphalt paving on the taxiway, apron and wash rack.
  • Continued water main installation along the entrance road.
  • Continued sanitary sewer installation along the entrance road.
  • Completed installation of trees and irrigation for the landscaping berm. Smaller plants will be installed later.
Work Completed, Week Ending 10/6/17:
  • Continued installing vertical panels on the plan east and north walls.
  • Continued bolt tightening.
  • Continued installing bracing in the mezzanine area.
  • Poured slab on grade under the middle mezzanine.
  • Poured blockouts for columns.
  • Continued end wall rough in.
  • Continued electrical installation of hangar lightning protection and grounding.
  • Continued installation of mechanical FRP duct and huffer pipe in the western portion of the hangar.
  • Continued installation of duct hangers.
  • Continued plumbing backfill and installation at the hangar door foundation.
  • Continued interior wall framing and began installation of drywall.
  • Installed pipe run between structures CD-1 and CD-2 in the drainage ditch running south of the hangar and sodded portions of this ditch.
  • Poured the headwall for structures S-005.
  • Completed airside paving and electrical installation for the taxiway tie-in.
  • Continued water main installation along the entrance road.
  • Continued sanitary sewer installation along the entrance road.
  • Began installation of landscaping on the berm, including trees and pine straw.
 

September 2017 Progress 


  
Work Completed, Week Ending 9/29/17:
  • Continued installing vertical panels on the box truss.
  • Continued installation of draft walls, girts and skylights.
  • Welded angles at columns.
  • Installed curbing for skylights.
  • Continued grading and paving preparation within the hangar.
  • Poured slab on deck in one area.
  • Continued end wall rough.
  • Continued electrical installation of hangar lightning protection and grounding.
  • Continued electrical rough in and lighting installation in the administrative area.
  • Continued installation of mechanical FRP duct and huffer pipe in the western portion of the hangar.
  • Continued plumbing installation and backfill.
  • Continued interior wall framing.
  • Continued installation of storm water pipe run.
  • Continued storm sewer work in the North parking lot area and backfilled.
  • Shaped and sodded shoulders along the taxiway.
  • Continued taxiway special tie-in, installing crack mitigation fabric today and beginning paving with asphalt.
  • Continued electrical installation at the taxiway/runway tie-in, pouring concrete pads for signage.
  • Continued sanitary sewer along the entrance road, installing pipe and structures.
Work Completed, Week Ending 9/22/17:
  • Continued installing vertical panels on the plan south face of the box truss.
  • Continued installation of draft walls, girts, and skylights.
  • Continued installation of studs for the middle mezzanine.
  • Installed decking and duct penetration block outs for the west mezzanine.
  • Continued grading and paving preparation within the hangar.
  • Continued electrical installation of hangar lightning protection and grounding.
  • Continued installation of mechanical FRP duct and huffer pipe.
  • Continued plumbing rough in and backfill and installed trap primers.
  • Continued berm construction and prepared for landscaping installation.
  • Began installation of pipe run connecting to existing storm structure EX-401.
  • Gulf Power set the pole for permanent power.
  • Samples from the concrete portion of the special taxiway tie-in at runway 17/35 will be tested for flexure.
  • Installed topsoil along the taxiway.
  • Continued lighting installation at the taxiway/runway.
  • Continued with installation of utilities at Langley Avenue and along the entrance road.
Work Completed, Week Ending 9/15/17:
  • Began installing vertical panels on the plan south face of the box truss.
  • Continued mezzanine erection.
  • Continued seaming roof panels.
  • Continued welding studs for the middle mezzanine.
  • Poured the slab on grade in areas.
  • Continued electrical installation, installed hangar lightning protection, and performed rough-in at the taxiway.
  • Continued installation of mechanical FRP duct and huffer pipe in the plan western portion of the hangar.
  • Continued installation of plumbing.
  • Performed well pointing in the north parking lot area for utilities installation and set structures. Began excavating outfall ditch running south from the hangar and began work to tie into existing structures EX-401.
  • Set storm structures near the wash rack.
  • Taxiway paving for asphalt P-403 layers.
  • Concrete portion of special taxiway tie-in at runway 17/35.
  • Continued grading at the taxiway.
  • Pour sidewalk at Langley Avenue.
Work Completed, Week Ending 9/8/17:
  • Continued installing girts and strapping in the high bay area.
  • Continued decking in the east and middle mezzanine areas.
  • Continued seaming roof panels.
  • Continued bolt inspection.
  • Continued electrical installation.
  • Continued installation of mechanical FRP duct in the western portion of the hangar.
  • Continued grading and compacting within the Northeast hangar area in preparation for concrete pacing.
  • Continued mezzanine column base plate grouting.
  • Continued installation of plumbing.
  • Performed well pointing in the North parking lot area for utilities installation.
  • Completed removal of old asphalt runway and fire access road.
  • Completed 2nd lift of asphalt paving on the apron and wash rack.
  • Continued taxiway tie-in work, installing subbase, starting paving, and installing duct bank.
  • Completed installation and testing of water line north of Langley Ave, set first fire hydrant and performed flow test 9/7/17.
Work Completed, Week Ending 9/1/17:
  • Continued installing girts and bracing in the low bay area.
  • Continued steel erection in the east and middle mezzanine areas.
  • Continued installing roof panels and insulation.
  • Continued electrical installation.
  • Continued installation of mechanical components in the western portion of the hangar.
  • Continued grading and installation of edge forming.
  • Continued column base plate grouting.
  • Continued installation of plumbing.
  • Continued removal of old asphalt runway and fire access road.
  • Continued taxiway tie-in work, installing subgrade and stabilized subgrade.
  • Continued work at Langley Avenue to complete installation of portion of new water line north of Langley.

August 2017 Progress 


  
Work Completed, Week Ending 8/25/17:
  • Continued installing girts and bracing in the low bay area.
  • Continued steel erection in the east and middle mezzanine areas.
  • Continued installing roof panels and insulation.
  • Continued electrical installation within administrative areas.
  • Began installation of mechanical components in the western portion of the hangar.
  • Continued installing storm sewer along the wash rack.
  • Continued grading within the northeast hangar area.
  • Poured the truck well.
  • Continued installation of plumbing.
  • Continued removal of old asphalt runway and fire access road.
  • Shut down runway 17/35 and began taxiway tie-in work: Began earthwork and fill of taxiway to build up sub-grade. Began electrical installation at taxiway.
  • Constructed P-403 test strip and will install P-401 test strip today.
  • Continued work at Langley avenue to install new water line.
Work Completed, Week Ending 8/18/17:
  • Continued installing girts and bracing in the low bay area.
  • continued steel erection in the east and middle mezzanine areas.
  • Continued installing roof panels and insulation.
  • Continued installing storm sewer pipe in the glide slope area.
  • Continued work in the truck well.
  • Continued installation of electrical in the northeast building area.
  • Began grading within the northeast building area.
  • Continued installation of plumbing in the northwest corner of the building.
  • Continued removal of old asphalt runway.
  • Continued work at Langley Avenue: performed boring and locating isolation valve with ECUA.
Work Completed, Week Ending 8/11/17:
  • Continued installing girts and bracing in the low bay area.
  • Began steel erection for the east mezzanine.
  • Continued installing roof panels and insulation.
  • Pressure washed steel in the high bay area.
  • Continued work in the truck well.
  • Continued installation of electrical conduit in north parking lot.
  • Began installation of electrical conduit in north parking lot.
  • Began installation of electrical in the east mezzanine.
  • Began installation of plumbing in the northwest corner of the building.
  • Continued removal of old asphalt runway.
  • Began mobilizing materials and equipment for utility work at Langley Ave.
Work Completed, Week Ending 8/4/17:
  • Continued installing girts and bracing in the low bay area.
  • Erected steel for the administrative area.
  • Continued installing roof panels and insulation.
  • Continued installing storm sewer pipe.
  • Began paving asphalt base layer in the apron area.
  • Installed new access gate in temporary security fence.
  • Continued work in the truck well; forming and tying rebar.
  • Removed forms from elevator pit walls. Installed waterproofing and backfilled.
  • Continued installation of electrical conduit in north parking lot.
  • Continued removal of old asphalt runway.

August 2017 Completed Work

 

July 2017 Progress 


  
Work Completed, Week Ending 7/28/17:
  • Completed low bay main frame and continued installing girts and bracing in the low bay area.
  • Continued testing bolts in the high bay area.
  • Continued installing roof panels and insulation.
  • Continued installing storm sewer pipe.
  • Continued grading, testing and proof-rolling in the wash rack and apron areas.
  • Continued work in the truck well.
  • Poured elevator pit walls.
  • Completed installation of electrical conduit along entrance road and continued installation of conduit in north parking lot.
  • Continued removal of old asphalt runway.
Work Completed, Week Ending 7/21/17:
  • Continued installing beams, girts and bracing in the low bay area.
  • Additional steel erection crew mobilized to install roof in the high bay area.
  • Continued pretensioning bolts in the high bay area.
  • Received deliveries of roof panels and insulation and began installing.
  • Continued grouting column bases.
  • Continued installing storm sewer pipe.
  • Continued grading, testing and proof-rolling in the wash rack and apron areas.
  • Obtained soil samples from Areas D and E for preliminary testing in preparation for work in these areas.
  • Continued work in the truck well; installing gravel and sand layers.
  • Continued installation of electrical conduit in north parking lot and along entrance road.
  • Continued removal of old asphalt runway.
Work Completed, Week Ending 7/14/17:
  • Continued installing beams, girts and bracing in the low bay area.
  • Continued pretensioning bolts.
  • Continued accepting deliveries of roof beams and bracing.
  • Continued installing storm sewer between pipe.
  • Continued grading and testing in the wash rack and apron areas.
  • Poured the elevator pit.
  • Continued installation of electrical conduit in north parking lot and along entrance road.
  • Continued initial repairs to anchor bolts damaged by fallen columns.
  • Continued removal of old asphalt runway.
  • Coordinated with FAA regarding work within the glide slope area.
Work Completed, Week Ending 7/7/17:
  • Continued pretensioning bolts.
  • Checked column plumbness.
  • Continued accepting deliveries of roof beams and bracing.
  • Continued cleaning and pressure washing steel.
  • Continued installing storm sewer.
  • Performed grading and testing in the wash rack and apron areas.
  • Well point installation for the elevator pit.
  • Continued installation of electrical conduit in north parking lot and along entrance road.
  • Continued repair to anchor bolts damaged by fallen columns.
  • Began demolition of abandoned asphalt runway.

July 2017 Completed Work

 

June 2017 Progress

  

Work Completed, Week Ending 6/30/17:
  • Continued installing beams, girts and bracing along building perimeter.
  • Continued pretension of bolts.
  • Checked column plumb.
  • Continued accepting deliveries of roof beams and bracing.
  • Continued installing storm sewer.
  • Performed grading and testing in the wash rack and apron areas.
  • Undercut the elevator pit to remove sediment deposition.
  • Poured piers.
  • Continued installation of electrical conduit in north parking lot and along entrance road.
  • Began chipping columns to investigate anchor bolts damaged by fallen columns.
  • Held asphalt pre-paving meeting.
  • Held concrete pre-paving meeting.
Work Completed, Week Ending 6/23/17:
  • Experienced delays due to rain and lightning.
  • Continued installing storm sewer between pipe.
  • Pressure washed steel.
  • Performed minimal grading in the wash rack and apron areas.
  • Performed dewater activities.
Work Completed, Week Ending 6/16/17:
  • Experienced delays due to rain and lightning.
  • Continued receiving deliveries of low bay steel.
  • Continued bolting high bay steel.
  • Performed bolt testing.
  • Continued installing storm sewer between pipe between structures.
  • Electrician continued installing conduit in north parking lot and along entrance road.
  • Continued grading in the wash rack and apron areas.
  • Performed maintenance of silt fence.
  • Continued dust control with water truck.
Work Completed, Week Ending 6/9/17:
  • Continued bolting high bay steel and installing purlins and braces.
  • Began receiving deliveries of low bay steel.
  • Continued installing storm sewer.
  • Wrecked forms, backfilled and compacted around footers in the administrative building area.
  • Electrician continued installing conduit in north parking lot and along entrance road.
  • Performed grading in the apron area.
  • Performed maintenance of silt fence.
  • Continued dust control with water truck.
Work Completed, Week Ending 6/2/17:
  • Continued bolting high bay steel and installing purlins.
  • Poured remaining interior spread footings, except for elevator pit.
  • Continued backfilling around apron storm structures and pipes.
  • Continued installing storm pipe.
  • Electrician continued installing conduit.
  • Performed maintenance of silt fence.
  • Continued dust control with water truck.

June 2017 Completed Work

 

May 2017 Progress
  


Work Completed, Week Ending 5/26/17:
  • Front box truss lifted and installed. Began installing roof purlins and bracing.
  • Poured remaining interior spread footings, except for elevator pit.
  • Formed rebar for administrative building footings.
  • Continued backfilling around apron storm structures and pipes.
  • Continued installing storm pipe and installed structure.
  • Electrician continued installing secondary conduit from the building to the transformer pad.
  • Performed maintenance of silt fence.
  • Continued dust control with water truck.
Work Completed, Week Ending 5/19/17:
  • Backfilled and compacted around previously poured interior spread footings.
  • Formed and installed rebar for remaining interior spread footings.
  • Continued backfilling around apron storm structures.
  • Started storm system tie-in to structure along the runway safety area line.
  • Continued assembly of steel box truss and began setting columns.
  • Continued dust control with water truck.
Work Completed, Week Ending 5/12/17:

  • Poured interior spread footings, except for the eight in the center of the building pad.
  • Performed prep work for center interior spread footings and elevator pit.
  • Completed installation of all apron storm drainage piping, except for between structures S-470 and S-560.
  • Continued installing electrical conduit for main feed in the admin area. 
  • Continued assembly of steel box truss.
  • Continued dust control with water truck
Work Completed, Week Ending 05/05/17:
  • Poured northwest interior spread footings and backfilled.
  • Poured remaining grade beams and backfilled.
  • Performed prep work for center interior spread footings.
  • Completed installation of storm drainage piping between S-470 and S-480 and began installing piping between structures S-480 and S-490.
  • Continued assembly of steel box truss.
  • Ran water truck for dust control.

May 2017 Completed Work

 

April 2017 Progress
   


Work Completed, Week Ending 04/28/17:
  • Poured northeast and northwest interior spread footings and backfilled.
  • Installed electrical conduit runs.
  • Installed storm drainage piping in apron area.
  • Continued to deliver and assemble steel.
Work Completed, Week Ending 04/21/17:
  • Backfilled foundation areas.
  • Formed and installed reinforcing in spread footings.
  • Received drainage structures.
  • Installed two drainage structures.
  • Started receipt and assembly of structural steel box beams.
Work Completed, Week Ending 04/14/17:
  • Completed pile cap 52 pour.
  • Stripped forms from previous pours and backfilled around pile caps.
  • Continued tying rebar for remaining grade beams.
  • Began excavating spread footings and tying rebar for footings.
  • Completed survey of all pile locations.
  • Began installing electrical stub-ups.
Work Completed, Week Ending 04/7/17:
  • Continued work on pile caps.
  • Excavated, placed fabric stone and set structure S-440.
  • Prepped for additional storm structures.
  • Laid conduits.
  • Performed layout for spread footings.

Upcoming Meeting Dates:


No upcoming meeting dates

Previous Meeting Dates:



10/28/2016: Groundbreaking Ceremony
 
9/9/2014: Special City Council Meeting – Approval of lease with VT MAE
Video Archive: http://pensacolafl.swagit.com/play/09092014-814  
Agenda: http://cityofpensacola.com/AgendaCenter/ViewFile/Agenda/09092014-691 
Minutes: http://cityofpensacola.com/AgendaCenter/ViewFile/Minutes/09092014-691 

3/20/2014: VT MAE Job Fair

2/25/2014: Public Meeting

FOR MORE INFORMATION, CONTACT:

Dan Flynn
Airport Director
(850) 436-5007
DFlynn@cityofpensacola.com

April 2017 Completed Work

 

March 2017 Progress 


Work Completed, Week Ending 03/31/17:
  • Forming and rebar at pile caps and grade beams.
  • Formed and poured mud slabs.
  • Backfilling pile caps and grade beams on East side.
  • Surveyed anchor bolts.
  • Layout for spread footings at administration area.
  • Installing grounding conduits.
Work Completed, Week Ending 03/24/17:
  • Continued forming and tying rebar for grade beams and pile caps.
  • Continued pouring concrete from pile caps and piers.
  • Received aircraft rated stormwater structures for the apron.
Work Completed, Week Ending 03/17/17:
  • Completed soil borings at stormwater structures in apron area.
  • Received stormwater structures for installation.
  • Corrected issues with rebar at pile caps.
  • Set anchor bolts.
  • Continued repairing short piles.
  • Continue forming and tying rebar for grade beams and pile caps.
Work Completed, Week Ending 03/10/17:
  • Continued repairing short piles.
  • Completed cutting to subgrade in all areas.
  • Continued forming and tying rebar for grade beams and pile caps.
  • Continued stripping forms from poured grade beams and pile caps to be reused for forming subsequent grade beams and pile caps. 
Work Completed, Week Ending 03/03/17:
  • Performed first concrete pour for grade beams and pile caps.
  • Continued repairing short piles.
  • Completed undercutting/de-mucking in wash rack area.
  • Continued backfilling and compaction in apron area.
  • Completed cutting apron area to grade.
  • Continued forming and tying rebar for grade beams and pile caps.
  • Began stripping forms from poured grade beams and pile caps to be reused for forming subsequent grade beams and pile caps.

March 2017 Completed Work

 

February

2017 Progress


Work Completed, Week Ending 02/24/17:
  • As-Built survey for pile locations completed.
  • Short pile correction is 60% completed.
  • Mud slab installation is 95% complete.
  • Temporary power transformer set.
  • Continued undercutting/de-mucking in wash rack area and apron area.
  • Began backfilling and compaction in apron area.
  • Continued forming and tying rebar for grade beams and pile caps.
Work Completed, Week Ending 02/17/17:
  • Demobilized pile rig and crane.
  • Continued as-built survey for installed piles.
  • Began repairing short piles.
  • Continued mud slab construction.
  • Continued undercutting/de-mucking in wash rack and apron area.
  • Continued forming and tying rebar for grade beams and pile caps.
  • Began backfilling and compaction in apron area.
Work Completed, Week Ending 02/03/17:
  • Continued installation of production piles, fabrication of cages and layout.
  • Continued pile cap excavation, well pointing and dewatering.
  • Continued undercutting/de-mucking in wash rack and apron area.

February 2017 Completed Work

 

January 2017 Progress



Work Completed, Week Ending 01/27/17:

  • Continued installation of production piles, fabrication of cages, and layout.
  • Continued pile cap excavation.
  • Started undercutting/de-mucking in wash rack area.
Work Completed, Week Ending 01/20/17:
  • Began installation of production piles, continued fabrication of cages and continued layout.
  • Continued pile cap excavation, well pointing, and de-watering.
  • Completed clearing and mulching.
  • Continued stripping topsoil in wash rack area.
Work Completed, Week Ending 01/13/17:
  • Test pile testing completed.
  • Mulching continued.
  • Excavation for pile caps and production pile layout is ongoing.
Work Completed, Week Ending 01/06/17:
  • Test piles construction completed.  Compression test completed.
  • ECUA approved 6” waterline tie for use on site.  Test results completed and accepted.
  • Pile cap excavation initiated and ongoing.  Rebar cages for pilings initiated.
  • Continuing large scale mulching activities for cleared debris.  Mulching to continue for approximately 2 weeks.
  • Submitted DRAFT landscape plan and grading plan to subcontractors for pricing.
  • Site security established and acceptable to the airport/FAA.
  • Dust abatement continuing on site.

January 2017 Completed Work

 

December 2016 Progress



Work Completed, Week Ending 12/16/16:
  • Gate installation completed.  Coordinated and completed airport security systems at gates (fiber optic and intrusion detection systems).
  • Completed grading at building pad.  Initiated excavation at building pad.  Hauling excavated material to stockpile.
  • Initiated proof rolling in the building pad area.
  • Continuing large scale mulching activities for cleared debris.
  • Gulf Power completed installation of temporary power. 
  • Relocated construction trailers.
  • Completed asphalt removal in building pad area.
  • Continued surveying and layout work on the project site.  Completed control points on south side of building pad.
  • Initiated excavation for access road from Langley Avenue to entrance gate.
  • Coordinated with airport’s landscape contractor for relocation of landscaping on Langley Avenue.
  • Dust abatement continuing on site.
Work Completed, Week Ending 12/09/16:
  • Completed temporary security fencing.  Coordinating construction entry gate with airport security systems.
  • Completed clearing and grubbing at building pad.
  • Completed silt fencing.
  • Continuing large scale mulching activities for cleared debris.
  • Coordinated with Gulf Power for temporary power. 
  • Relocated construction trailers.
  • Completed asphalt removal in building pad area.
  • Continued surveying and layout work on the project site.  Setting elevations on south side of building pad.
  • Dust abatement continuing on site.
Work Completed, Week Ending 12/02/16:
  • Completed clearing and grubbing of building pad area.
  • Completed security fencing with the exception of gates.
  • Clearing and grubbing ongoing.
  • Silt fencing approximately 90% complete.  Silt fencing was installed in accordance with revisions 6 & 7 issued by the A/E.
  • Large scale mulching activities ongoing for cleared debris.
  • Coordinated with Gulf Power for temporary power and transformer.
  • Surveying and layout work on the project site continued throughout the week.
  • Dust abatement continuing on site.
  • Removing existing asphalt and concrete at the building pad location.
  • Clearing site at the entrances completed.

December 2016 Completed Work

 

November 2016 Progress



Work Completed, Week Ending 11/18/16:
  • Completed approximately 95% of the temporary security fencing.
  • Clearing and grubbing ongoing.
  • Silt fencing ongoing based upon the 95% documents.
  • Large scale mulching activities ongoing for cleared debris.
  • Coordinated with Gulf Power for removal of abandoned lines and temporary power.
  • Surveying and layout work on the project site continued throughout the week and is anticipated to be complete next week.
  • Dust abatement continuing on site.
  • Project construction sign installed on Langley Avenue.
  • Clearing site at the building pad location.
  • Clearing site at the entrances.
Work Completed, Week Ending 11/11/16:
  • Three (3) gopher tortoise burrows have been located and protection provided per the construction documents.  One burrow was located on the work site and two additional burrows were located on the other side of the perimeter road.   Two additional burrows located near the proposed stockpile will be monitored and protected if necessary.  Construction access and egress from the proposed stockpile location will be limited to designated routes.
  • Layout work on the project site continued throughout the week and is anticipated to be complete next week.
  • Continued work on the clearing and grubbing of the site.
  • Security fencing work continued throughout the week and is anticipated to be completed by the end of next week with the exception of the gates.
  • CMAR superintendent’s job site single wide trailer was mobilized on site.  Anticipate mobilization of project doublewide trailer next week.

November 2016 Completed Work

 

October 2016 Progress



Work Completed, Week Ending 10/14/16:

  • CMAR has received all executed contract documents required from the City.
  • CMAR has obtained the building permit from the City.
  • CMAR is anticipating the NTP for Monday, October 17, 2016 and will mobilize site contractors to initiate project layout.
  • An introductory meeting with the CMAR team and CA team inspectors/administrators will be held on Monday, October 17, 2016 at 1:30pm at the offices of Greenhut.
  • The CMAR has scheduled the pre-construction conference for October 27, 2016 at 2:00 pm.  The pre-construction meeting will be held at the airport conference room.   A draft agenda will be distributed by the CMAR for review and comment by the design team and CA team.
  • The CMAR will confirm the cost of “Additive Alternate No. 1” as requested by VTMAE during the last VE meeting and distribute to the CA.
  • The CMAR will update the construction schedule with dates based upon an NTP of October 17, 2016.